The critical path is the path through the project network in which none of the activities have _______, that is, the path for which ________ for all activities in the path.
A) sack / AS = FS and FE = FL
B) compression / CS = LS and CE = LF
C) better timed / LS = ES and LF = EF
D) crashed / SE = SL and FE = FL
E) slack / ES = LS and EF = LF
Correct Answer:
Verified
Q36: _ is described as follows: Some activities
Q37: The steps in the CPM project planning
Q38: Gantt charts (or Bar charts) are useful
Q39: The CPM network consists of arcs and
Q40: The CPM establishes:
A) The quantity of work
Q42: The _ for an activity is the
Q43: Speeding up the project is referred to
Q44: delay in the critical path delays the
Q45: _ is the amount of time that
Q46: LS - latest start time can be