___________ Is Described as Follows: Some Activities Are Concurrent with Other

Question 36

Multiple Choice

___________ is described as follows: Some activities are concurrent with other activities. A listing of the immediate predecessors of each activity is useful for constructing the CPM network diagram.


A) Identify the critical path (longest path through the network)
B) Sequence the activities
C) Specify each individual activity
D) Draw a network diagram
E) Update the CPM diagram as the project progresses