The following selected information was extracted from the accounting records of Austin, Inc.:
Planned manufacturing activity: 40,000 machine hours
Standard variable-overhead rate per machine hour: $16
Budgeted fixed overhead: $100,000
Variable-overhead spending variance: $92,000U
Variable-overhead efficiency variance: $102,000F
Fixed-overhead budget variance: $25,000U
Total actual overhead: $675,000
Required:
Determine the following: actual fixed overhead, actual variable overhead, actual machine hours worked, standard machine hours allowed for actual production, and the fixed-overhead volume variance.
Correct Answer:
Verified
Actual v...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q78: Draco, Inc. has the following overhead standards:
Variable
Q79: Bavaria's budget for variable overhead and fixed
Q80: Master Products has the following information for
Q82: Hunters, Inc. uses a standard cost system
Q84: Hanks Company uses a standard cost system
Q86: The following information relates to Joplin
Q87: Briefly explain the nature of the fixed-overhead
Q87: Hot Stuff operates a delivery service for
Q88: A production manager was recently given a
Q89: Briefly describe the procedures that are used
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents