Draco, Inc. has the following overhead standards:
Variable overhead: 4 hours at $8 per hour
Fixed overhead: 4 hours at $10 per hour
The standards were based on a planned activity of 20,000 machine hours when 5,000 units were scheduled for production. Actual data follow.
Variable overhead incurred: $167,750
Fixed overhead incurred: $210,000
Machine hours worked: 19,800
Actual units produced: 5,100
Draco's fixed-overhead volume variance is:
A) $4,000 favorable.
B) $4,000 unfavorable.
C) $10,000 favorable.
D) $10,000 unfavorable.
E) None of the other answers are correct.
Correct Answer:
Verified
Q66: When actual variable cost per unit equals
Q73: The sales-volume variance equals:
A) (actual sales volume
Q74: Draco, Inc. has the following overhead standards:
Variable
Q75: Riskless Insurance uses budgets to forecast and
Q77: Draco, Inc. has the following overhead standards:
Variable
Q79: Bavaria's budget for variable overhead and fixed
Q80: Master Products has the following information for
Q82: Hunters, Inc. uses a standard cost system
Q83: The following selected information was extracted from
Q87: Briefly explain the nature of the fixed-overhead
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents