EV-AC =
A) Cost performance index CPI)
B) Scheduled performance index SPI)
C) Cost Variance CV)
D) Minimum funds needed MFN)
E) None of the above
Correct Answer:
Verified
Q21: Schedule Variance (SV) is _
A) how much
Q22: Barring a change in project scope and
Q32: Actual Cost AC is _
A)how much we
Q33: Budget At Completion BAC is _
A)how much
Q36: Barring a change in project scope and
Q37: In Project Communications Management,providing relevant and timely
Q40: Estimate at Completion (EAC) is _
A) how
Q40: In Project Communications Management,ensuring that clear,consistent,and timely
Q53: A _ predicts the future status or
Q56: A _ describes the present state of