Once the project is approved and moves into the planning stage, _____.
A) agreements for risk sharing need to be concluded
B) the total risk on the project typically reduces as activities are performed without loss
C) risks must be weighed against the potential benefit of the project's success in order to decide if the project should be chosen
D) risks are identified with each major group of activities
E) a risk response plan can be used to identify increasing levels of detailed risk analysis
Correct Answer:
Verified
Q53: _ risks are events that have been
Q54: What is the difference between project risk
Q55: High scores for internal complexity imply high
Q56: High scores for environmental complexity imply high
Q57: During the closeout phase, _.
A) risks must
Q59: Risk must be considered in the _
Q60: Describe the impact of high scores in
Q61: Projects that have a high score in
Q62: During the closeout phase, agreements for risk
Q63: _ includes both the identification of potential
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents