Solved

Once the Project Is Approved and Moves into the Planning

Question 58

Multiple Choice

Once the project is approved and moves into the planning stage, _____.


A) agreements for risk sharing need to be concluded
B) the total risk on the project typically reduces as activities are performed without loss
C) risks must be weighed against the potential benefit of the project's success in order to decide if the project should be chosen
D) risks are identified with each major group of activities
E) a risk response plan can be used to identify increasing levels of detailed risk analysis

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents