Risk Must Be Considered in the _____ Phase and Weighed

Question 59

Multiple Choice

Risk must be considered in the _____ phase and weighed against the potential benefit of the project's success in order to decide if the project should be chosen.


A) completion
B) closeout
C) execution
D) planning
E) initiation