Question 61
Multiple Choice
Positive slack indicates the maximum amount of time
Question 62
Multiple Choice
Total slack is calculated for each of the activities by finding the difference between
Question 63
Multiple Choice
As the project progresses, the actual finish times (AFs) of completed activities will determine
Question 64
Multiple Choice
The project control process involves all of the following except
Question 65
Multiple Choice
The key to effective project control is measuring actual progress and comparing it to planned progress on a timely and regular basis and
Question 66
Multiple Choice
Schedule control involves four steps. Place these steps in their proper order by stating the letter sequence of their proper order.
Question 67
Essay
Schedule control involves four steps. List the four steps in order.
Question 68
Multiple Choice
If the planned corrective actions do not result in an acceptable schedule, then
Question 69
Multiple Choice
Free slack is the amount of time a specific activity can be
Question 70
Multiple Choice
A concentrated effort to accelerate project progress must be applied to the paths with negative slack to activities that
Question 71
Multiple Choice
The estimated duration for each activity is indicated by a bar spanning the period
Question 72
Multiple Choice
Eliminating negative slack by reducing durations of activities will involve a trade-off in the form of
Question 73
Multiple Choice
The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task C is planned to take eight days. The tasks have a serial relationship. Task A takes nine days to be completed instead of seven days. How much slack does the project have now that Task A is finished?
Question 74
Multiple Choice
The project control process must occur regularly throughout the project and include all of the following except
Question 75
Multiple Choice
With respect to the project schedule, changes can result in any of the following except
Question 76
Multiple Choice
Negative slack indicates a lack of slack over the entire project and the amount of time
Question 77
Multiple Choice
The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task C is planned to take eight days. The tasks have a serial relationship. How much slack does the project have?