Question 61
True/False
The range of a data set is always non-negative.
Question 62
True/False
An important task in quality control is to find out the range of natural random variation in a process.
Question 63
Multiple Choice
Which of the following is the least important point to perform inspection?
Question 64
Multiple Choice
Suppose that you have calculated the control limits for a p-chart to be the following: LCL = 0.02 and UCL = 0.08. Today,you took 10 samples of 20 units each.The first nine samples each had one defect.The last sample had zero defects.What can you conclude?
Question 65
Multiple Choice
What is the upper control limit for a c-chart if the total defects found over 200 samples equals 32?
Question 66
True/False
Statistical quality control is a subset of statistical process control.
Question 67
True/False
Acceptance sampling occurs after the product has been produced.
Question 68
Multiple Choice
What is the lower control limit for a c-chart if the average number of defects found over 320 samples is equal to 16?
Question 69
Multiple Choice
What program at Intel enforces the policy to make chips in the same way at all facilities?
Question 70
Multiple Choice
If the upper control limit for a c-chart is 28 and the lower control limit is 4,what is the average number of defects per sample?
Question 71
True/False
Descriptive statistics are used to describe quality characteristics and relationships.
Question 72
Multiple Choice
Each day for two workweeks (10 days total) ,George weighs 4 bags from that day's production.If the average of the means is 14 oz.and the average range is 0.4 oz.,what is the lower control limit for an x-bar chart for this process?
Question 73
Multiple Choice
What is the upper control limit for a c-chart if the total defects found over 20 samples equals 150?
Question 74
Multiple Choice
What is the only service company to have won the Malcolm Baldrige National Quality Award twice?
Question 75
Multiple Choice
Ritz-Carlton employees are empowered to spend up to how much money on the spot to correct any customer complaint?
Question 76
Multiple Choice
Suppose that you want to measure the percentage of candles that are cut longer than 9 inches.Which control chart would be appropriate?
Question 77
Multiple Choice
Suppose that you want to monitor the average ounces of a process that fills beer cans.Which control chart would be appropriate?
Question 78
True/False
The standard deviation measures the difference between the largest and smallest observations in a set of data.
Question 79
Multiple Choice
Suppose that Matt wants to use a process control chart to monitor the number of different types of mistakes that he makes when giving motivational speeches to student groups.Which control chart would be most appropriate?