What Resources Have Been Initially Over-Allocated in the Project Described

Question 99

Essay

What resources have been initially over-allocated in the project described by the table? Assume that all activities will begin at their early start times and require the number of hours per day indicated in the table.Each worker is available for 8 hours per day.Do not level this project.
 Activity  Activity  Length  Predecessor  Resource  Resource  Hours Per Day  A 9 Lisa 1 B 8 Nathan 7 C 13 A  Take 6 D 11 B  Nathan 6 E 6 B  Take 4 F 9 C  Lisa 4G9 D  Take 5 H 9 E  Lisa 6M9 F, G  Nathan 7J4 F, H  Lisa 2 K 1 M, J  Nathan 6L11 K  Take 7\begin{array} { | l | l | l | l | l | } \hline \text { Activity } & \begin{array} { l } \text { Activity } \\\text { Length }\end{array} & \text { Predecessor } & \text { Resource } & \begin{array} { l } \text { Resource } \\\text { Hours Per Day }\end{array} \\\hline \text { A } & 9 & - & \text { Lisa } & 1 \\\hline \text { B } & 8 & - & \text { Nathan } & 7 \\\hline \text { C } & 13 & \text { A } & \text { Take } & 6 \\\hline \text { D } & 11 & \text { B } & \text { Nathan } & 6 \\\hline \text { E } & 6 & \text { B } & \text { Take } & 4 \\\hline \text { F } & 9 & \text { C } & \text { Lisa } & 4 \\\hline G & 9 & \text { D } & \text { Take } & 5 \\\hline \text { H } & 9 & \text { E } & \text { Lisa } & 6 \\\hline M & 9 & \text { F, G } & \text { Nathan } & 7 \\\hline \text {J} & 4 & \text { F, H } & \text { Lisa } & 2 \\\hline \text { K } & 1 & \text { M, J } & \text { Nathan } & 6 \\\hline L & 11 & \text { K } & \text { Take } & 7 \\\hline\end{array}

Correct Answer:

verifed

Verified

Resource loadings are summariz...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents