A company is using a Kanban system with 2 containers, each holding 50 parts, between a downstream (using) and an upstream (producing) work center.The using work center can handle 250 jobs per day.The average elapsed time for the entire cycle is currently .25 days.The company is concerned with the safety factor for the operation and the size of the containers.
a.What is the efficiency rating of the current operation?
b.If the company decides to use only one container, how many parts must it hold?
c.If the safety factor is changed to .12 and there are still 2 containers, how many parts must each container now hold?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q53: A manufacturer of automobile engines is
Q54: Discuss the seven major categories of waste
Q55: Which one of the following statements is
Q56: ABC Manufacturing uses a Kanban system for
Q57: Which one of the following statements is
Q58: Southwest Airlines illustrates the application of "lean
Q59: Hinge Manufacturing Company employs a Kanban
Q60: Which of the following "lean" ideas is
Q61: A company is using Kanban containers.There
Q62: A manufacturing company is using a two-container
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents