Activities should ____ the time intervals at which actual project progress will be reviewed and compared to planned progress.
A) not be longer in estimated duration than
B) be the same length in estimated duration as
C) be longer in estimated duration than
D) be any length of time, it doesn't matter the length
Correct Answer:
Verified