An activity in a network diagram cannot start until
A) all of the preceding activities that are linked to it by arrows are finished.
B) most of the preceding activities that are linked to it by arrows are finished.
C) none of the preceding activities that are linked to it by arrows are finished.
D) at least one of the preceding activities that are linked to it by arrows are finished.
Correct Answer:
Verified
Q99: It is important to plan for _
Q100: A comprehensive project scope document is _
Q101: It is common to progressively elaborate the
Q102: The responsibility assignment matrix may use a
Q103: The _ shows all the individuals associated
Q105: Standard subnetworks should be developed for those
Q106: A network diagram is a tool for
Q107: The _ is a roadmap that displays
Q108: To draw a _, start by drawing
Q109: _ contains a small number of higher-level
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents