You Are Responsible for Managing an Advertising Project with the Following

Question 33

Multiple Choice

You are responsible for managing an advertising project with the following activities (times are given in weeks) .
 Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)   (Weeks)   Cost ($)  Cost ($)  A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A, B 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  D. E F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$) \\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A, B } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { D. E F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array} Draw the project network here. BLANK SPACES
-If activity D is delayed by 2 weeks, which one of the following statements is TRUE?


A) There are now two critical paths in the network.
B) The slack time for activity D changes to 1 week.
C) The project completion time is still 14 weeks.
D) The project completion time becomes 18 weeks.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents