Which one of the following statements about the critical path method (CPM) is TRUE?
A) The activity time estimates are accurate and stable.
B) Activities are dependent on each other.
C) Activities can be interrupted before completion.
D) The project schedule defines a correct sequence of work in terms of technology and workflow.
Correct Answer: