Patton's Manufacturing Has Provided the Following Information Relating to a Large

Question 143

Essay

Patton's Manufacturing has provided the following information relating to a large order of Part #2347 transistors for a major customer:
Raw materials ordered for Part #2347 July 1st
Part #2347 put into production July 12th
Part #2347 completed July 13th
Part #2347 transferred to finished goods July 14th
Date order accepted July 15th
Order assembled July 17th,July 18th,July 19th
Order delivered to warehouse July 21st.
Warehouse packaged order July 23
Call to customer that order was ready July 24th
Customer picked up order July 24th
What is the delivery cycle time?
Appendix,

Correct Answer:

verifed

Verified

July 1st thr...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents