Services
Discover
Homeschooling
Ask a Question
Log in
Sign up
Filters
Done
Question type:
Essay
Multiple Choice
Short Answer
True False
Matching
Topic
Statistics
Study Set
Operations and Supply Chain Management Study Set 1
Quiz 3: Process Choice and Layout Decisions in Manufacturing and Services
Path 4
Access For Free
Share
All types
Filters
Study Flashcards
Practice Exam
Learn
Question 61
Multiple Choice
The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time and predecessor as shown in the table. They work a 7 hour day and want to produce at a rate of 360 units per day. What should their takt time be?
 TaskÂ
 TimeÂ
(
s
e
c
)
 PredecessorÂ
 AÂ
45
⋯
 BÂ
50
 AÂ
 CÂ
40
 AÂ
 DÂ
55
 B, CÂ
 EÂ
40
 DÂ
 FÂ
65
 DÂ
 GÂ
25
 EÂ
 HÂ
35
 F, GÂ
\begin{array} { | c | c | c | } \hline \text { Task } & \text { Time } ( \mathrm { sec } ) & \text { Predecessor } \\\hline \text { A } & 45 & \cdots \\\hline \text { B } & 50 & \text { A } \\\hline \text { C } & 40 & \text { A } \\\hline \text { D } & 55 & \text { B, C } \\\hline \text { E } & 40 & \text { D } \\\hline \text { F } & 65 & \text { D } \\\hline \text { G } & 25 & \text { E } \\\hline \text { H } & 35 & \text { F, G } \\\hline\end{array}
 TaskÂ
 AÂ
 BÂ
 CÂ
 DÂ
 EÂ
 FÂ
 GÂ
 HÂ
​
 TimeÂ
(
sec
)
45
50
40
55
40
65
25
35
​
 PredecessorÂ
⋯
 AÂ
 AÂ
 B, CÂ
 DÂ
 DÂ
 EÂ
 F, GÂ
​
​
Question 62
Multiple Choice
Use this scenario for the following question(s) . The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time, and predecessor as shown in the table. There are 7.5 productive hours available in a day and the manufacturer wishes to produce 400 units. Balance the line by assigning tasks to workstations to fill up as much takt time as possible. Break ties by assigning the longest task first.
 TaskÂ
 TimeÂ
(
s
e
c
)
 PredecessorÂ
 AÂ
45
⋯
 BÂ
50
 AÂ
 CÂ
20
 AÂ
 DÂ
55
 AÂ
 EÂ
15
 DÂ
 FÂ
65
 DÂ
 GÂ
25
 EÂ
 HÂ
35
 B, C, F, GÂ
\begin{array} { | c | c | c | } \hline \text { Task } & \text { Time } ( \mathrm { sec } ) & \text { Predecessor } \\\hline \text { A } & 45 & \cdots \\\hline \text { B } & 50 & \text { A } \\\hline \text { C } & 20 & \text { A } \\\hline \text { D } & 55 & \text { A } \\\hline \text { E } & 15 & \text { D } \\\hline \text { F } & 65 & \text { D } \\\hline \text { G } & 25 & \text { E } \\\hline \text { H } & 35 & \text { B, C, F, G } \\\hline\end{array}
 TaskÂ
 AÂ
 BÂ
 CÂ
 DÂ
 EÂ
 FÂ
 GÂ
 HÂ
​
 TimeÂ
(
sec
)
45
50
20
55
15
65
25
35
​
 PredecessorÂ
⋯
 AÂ
 AÂ
 AÂ
 DÂ
 DÂ
 EÂ
 B, C, F, GÂ
​
​
-Refer to the scenario above. Without using more than one worker per station, what is the maximum output achievable in the 7.5 hour work day?
Question 63
Multiple Choice
Use this scenario for the following question(s) . The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time, and predecessor as shown in the table. There are 7.5 productive hours available in a day and the manufacturer wishes to produce 400 units. Balance the line by assigning tasks to workstations to fill up as much takt time as possible. Break ties by assigning the longest task first.
 TaskÂ
 TimeÂ
(
s
e
c
)
 PredecessorÂ
 AÂ
45
⋯
 BÂ
50
 AÂ
 CÂ
20
 AÂ
 DÂ
55
 AÂ
 EÂ
15
 DÂ
 FÂ
65
 DÂ
 GÂ
25
 EÂ
 HÂ
35
 B, C, F, GÂ
\begin{array} { | c | c | c | } \hline \text { Task } & \text { Time } ( \mathrm { sec } ) & \text { Predecessor } \\\hline \text { A } & 45 & \cdots \\\hline \text { B } & 50 & \text { A } \\\hline \text { C } & 20 & \text { A } \\\hline \text { D } & 55 & \text { A } \\\hline \text { E } & 15 & \text { D } \\\hline \text { F } & 65 & \text { D } \\\hline \text { G } & 25 & \text { E } \\\hline \text { H } & 35 & \text { B, C, F, G } \\\hline\end{array}
 TaskÂ
 AÂ
 BÂ
 CÂ
 DÂ
 EÂ
 FÂ
 GÂ
 HÂ
​
 TimeÂ
(
sec
)
45
50
20
55
15
65
25
35
​
 PredecessorÂ
⋯
 AÂ
 AÂ
 AÂ
 DÂ
 DÂ
 EÂ
 B, C, F, GÂ
​
​
-Refer to the scenario above. What is the takt time?
Question 64
Short Answer
Name a service business that relies heavily on intangible activities. How does the level of intangibility fit with the degrees of contact and customization?
Question 65
Multiple Choice
Use this scenario for the following question(s) . The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time, and predecessor as shown in the table. There are 7.5 productive hours available in a day and the manufacturer wishes to produce 400 units. Balance the line by assigning tasks to workstations to fill up as much takt time as possible. Break ties by assigning the longest task first.
 TaskÂ
 TimeÂ
(
s
e
c
)
 PredecessorÂ
 AÂ
45
⋯
 BÂ
50
 AÂ
 CÂ
20
 AÂ
 DÂ
55
 AÂ
 EÂ
15
 DÂ
 FÂ
65
 DÂ
 GÂ
25
 EÂ
 HÂ
35
 B, C, F, GÂ
\begin{array} { | c | c | c | } \hline \text { Task } & \text { Time } ( \mathrm { sec } ) & \text { Predecessor } \\\hline \text { A } & 45 & \cdots \\\hline \text { B } & 50 & \text { A } \\\hline \text { C } & 20 & \text { A } \\\hline \text { D } & 55 & \text { A } \\\hline \text { E } & 15 & \text { D } \\\hline \text { F } & 65 & \text { D } \\\hline \text { G } & 25 & \text { E } \\\hline \text { H } & 35 & \text { B, C, F, G } \\\hline\end{array}
 TaskÂ
 AÂ
 BÂ
 CÂ
 DÂ
 EÂ
 FÂ
 GÂ
 HÂ
​
 TimeÂ
(
sec
)
45
50
20
55
15
65
25
35
​
 PredecessorÂ
⋯
 AÂ
 AÂ
 AÂ
 DÂ
 DÂ
 EÂ
 B, C, F, GÂ
​
​
-Refer to the scenario above. The process design team realizes that the potential spike in demand for this device requires increased output. They elect to add a seventh worker to their production team at the first station. What is the net effect of adding this worker?
Question 66
Multiple Choice
The table depicts a production line that has been balanced with a takt time of 2 minutes. What is the efficiency of this balance?
 WorkstationÂ
1
2
3
4
5
6
 TaskÂ
A
,
B
C
D
,
E
,
F
G
,
H
I
J
,
K
,
L
 TimeÂ
(
m
i
n
)
1
,
1
1.8
1
,
0.5
,
0.4
0.9
,
0.8
1.8
0.5
,
0.5
,
0.6
\begin{array} { | l | c | c | c | c | c | c | } \hline \text { Workstation } & 1 & 2 & 3 & 4 & 5 & 6 \\\hline \text { Task } & \mathrm { A } , \mathrm { B } & \mathrm { C } & \mathrm { D } , \mathrm { E } , \mathrm { F } & \mathrm { G } , \mathrm { H } & \mathrm { I } & \mathrm { J } , \mathrm { K } , \mathrm { L } \\\hline \text { Time } ( \mathrm { min } ) & 1,1 & 1.8 & 1,0.5,0.4 & 0.9,0.8 & 1.8 & 0.5,0.5,0.6 \\\hline\end{array}
 WorkstationÂ
 TaskÂ
 TimeÂ
(
min
)
​
1
A
,
B
1
,
1
​
2
C
1.8
​
3
D
,
E
,
F
1
,
0.5
,
0.4
​
4
G
,
H
0.9
,
0.8
​
5
I
1.8
​
6
J
,
K
,
L
0.5
,
0.5
,
0.6
​
​
Question 67
Multiple Choice
Use this scenario for the following question(s) . The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time, and predecessor as shown in the table. There are 8 productive hours available in a day and the manufacturer wishes to produce 400 units. Use this information to answer the following question(s) .
 TaskÂ
 TimeÂ
(
s
e
c
)
 PredecessorÂ
J
45
⋯
 KÂ
50
Â
J
L
40
Â
J
M
55
Â
K
,
Â
L
N
40
M
O
65
M
 PÂ
25
Â
N
 RÂ
35
O
,
P
\begin{array} { | c | c | c | } \hline \text { Task } & \text { Time } ( \mathrm { sec } ) & \text { Predecessor } \\\hline \mathrm { J } & 45 & \cdots \\\hline \text { K } & 50 & \mathrm {~J} \\\hline \mathrm { L } & 40 & \mathrm {~J} \\\hline \mathrm { M } & 55 & \mathrm {~K} , \mathrm {~L} \\\hline \mathrm { N } & 40 & \mathrm { M } \\\hline \mathrm { O } & 65 & \mathrm { M } \\\hline \text { P } & 25 & \mathrm {~N} \\\hline \text { R } & 35 & \mathrm { O } , \mathrm { P } \\\hline\end{array}
 TaskÂ
J
 KÂ
L
M
N
O
 PÂ
 RÂ
​
 TimeÂ
(
sec
)
45
50
40
55
40
65
25
35
​
 PredecessorÂ
⋯
Â
J
Â
J
Â
K
,
Â
L
M
M
Â
N
O
,
P
​
​
-Refer to the scenario above. What is the theoretical minimum number of stations?
Question 68
Essay
Name two restaurants that score differently on at least two scales in the service positioning space and provide examples of how they differ.
Question 69
Multiple Choice
Use this scenario for the following question(s) . The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time, and predecessor as shown in the table. There are 8 productive hours available in a day and the manufacturer wishes to produce 400 units. Use this information to answer the following question(s) .
 TaskÂ
 TimeÂ
(
s
e
c
)
 PredecessorÂ
J
45
⋯
 KÂ
50
Â
J
L
40
Â
J
M
55
Â
K
,
Â
L
N
40
M
O
65
M
 PÂ
25
Â
N
 RÂ
35
O
,
P
\begin{array} { | c | c | c | } \hline \text { Task } & \text { Time } ( \mathrm { sec } ) & \text { Predecessor } \\\hline \mathrm { J } & 45 & \cdots \\\hline \text { K } & 50 & \mathrm {~J} \\\hline \mathrm { L } & 40 & \mathrm {~J} \\\hline \mathrm { M } & 55 & \mathrm {~K} , \mathrm {~L} \\\hline \mathrm { N } & 40 & \mathrm { M } \\\hline \mathrm { O } & 65 & \mathrm { M } \\\hline \text { P } & 25 & \mathrm {~N} \\\hline \text { R } & 35 & \mathrm { O } , \mathrm { P } \\\hline\end{array}
 TaskÂ
J
 KÂ
L
M
N
O
 PÂ
 RÂ
​
 TimeÂ
(
sec
)
45
50
40
55
40
65
25
35
​
 PredecessorÂ
⋯
Â
J
Â
J
Â
K
,
Â
L
M
M
Â
N
O
,
P
​
​
-Refer to the scenario above. The manager assigns tasks to workstations and breaks ties using a longest operation heuristic. That is, if two or three tasks could be assigned to a given station, the manager assigns the longest task first and then fills in the remaining time at the workstation as completely as possible. Using this approach, what task(s) would be assigned at the fourth station?
Question 70
Multiple Choice
The table depicts a production line that has been balanced with a takt time of 2 minutes. What is the percent idle time of this balance?
 WorkstationÂ
1
2
3
4
5
6
 TaskÂ
A
,
B
C
D
,
E
,
F
G
,
H
I
J
,
K
,
L
 TimeÂ
(
m
i
n
)
1
,
1
1.8
1
,
0.5
,
0.4
0.9
,
0.8
1.8
0.5
,
0.5
,
0.6
\begin{array} { | l | c | c | c | c | c | c | } \hline \text { Workstation } & 1 & 2 & 3 & 4 & 5 & 6 \\\hline \text { Task } & \mathrm { A } , \mathrm { B } & \mathrm { C } & \mathrm { D } , \mathrm { E } , \mathrm { F } & \mathrm { G } , \mathrm { H } & \mathrm { I } & \mathrm { J } , \mathrm { K } , \mathrm { L } \\\hline \text { Time } ( \mathrm { min } ) & 1,1 & 1.8 & 1,0.5,0.4 & 0.9,0.8 & 1.8 & 0.5,0.5,0.6 \\\hline\end{array}
 WorkstationÂ
 TaskÂ
 TimeÂ
(
min
)
​
1
A
,
B
1
,
1
​
2
C
1.8
​
3
D
,
E
,
F
1
,
0.5
,
0.4
​
4
G
,
H
0.9
,
0.8
​
5
I
1.8
​
6
J
,
K
,
L
0.5
,
0.5
,
0.6
​
​
Question 71
Multiple Choice
The table depicts an production line that has been balanced with a takt time of 2 minutes. Where would you add a worker if you wanted to increase the output rate while keeping six work stations?
 WorkstationÂ
1
2
3
4
5
6
 TaskÂ
A
,
B
C
D
,
E
,
F
G
,
H
I
J
,
K
,
L
 TimeÂ
(
m
i
n
)
1
,
1
1.8
1
,
0.5
,
0.4
0.9
,
0.8
1.8
0.5
,
0.5
,
0.6
\begin{array} { | l | c | c | c | c | c | c | } \hline \text { Workstation } & 1 & 2 & 3 & 4 & 5 & 6 \\\hline \text { Task } & \mathrm { A } , \mathrm { B } & \mathrm { C } & \mathrm { D } , \mathrm { E } , \mathrm { F } & \mathrm { G } , \mathrm { H } & \mathrm { I } & \mathrm { J } , \mathrm { K } , \mathrm { L } \\\hline \text { Time } ( \mathrm { min } ) & 1,1 & 1.8 & 1,0.5,0.4 & 0.9,0.8 & 1.8 & 0.5,0.5,0.6 \\\hline\end{array}
 WorkstationÂ
 TaskÂ
 TimeÂ
(
min
)
​
1
A
,
B
1
,
1
​
2
C
1.8
​
3
D
,
E
,
F
1
,
0.5
,
0.4
​
4
G
,
H
0.9
,
0.8
​
5
I
1.8
​
6
J
,
K
,
L
0.5
,
0.5
,
0.6
​
​
Question 72
Multiple Choice
Use this scenario for the following question(s) . The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time, and predecessor as shown in the table. There are 7.5 productive hours available in a day and the manufacturer wishes to produce 400 units. Balance the line by assigning tasks to workstations to fill up as much takt time as possible. Break ties by assigning the longest task first.
 TaskÂ
 TimeÂ
(
s
e
c
)
 PredecessorÂ
 AÂ
45
⋯
 BÂ
50
 AÂ
 CÂ
20
 AÂ
 DÂ
55
 AÂ
 EÂ
15
 DÂ
 FÂ
65
 DÂ
 GÂ
25
 EÂ
 HÂ
35
 B, C, F, GÂ
\begin{array} { | c | c | c | } \hline \text { Task } & \text { Time } ( \mathrm { sec } ) & \text { Predecessor } \\\hline \text { A } & 45 & \cdots \\\hline \text { B } & 50 & \text { A } \\\hline \text { C } & 20 & \text { A } \\\hline \text { D } & 55 & \text { A } \\\hline \text { E } & 15 & \text { D } \\\hline \text { F } & 65 & \text { D } \\\hline \text { G } & 25 & \text { E } \\\hline \text { H } & 35 & \text { B, C, F, G } \\\hline\end{array}
 TaskÂ
 AÂ
 BÂ
 CÂ
 DÂ
 EÂ
 FÂ
 GÂ
 HÂ
​
 TimeÂ
(
sec
)
45
50
20
55
15
65
25
35
​
 PredecessorÂ
⋯
 AÂ
 AÂ
 AÂ
 DÂ
 DÂ
 EÂ
 B, C, F, GÂ
​
​
-Refer to the scenario above. What task(s) should be assigned at the third workstation?
Question 73
Multiple Choice
Use this scenario for the following question(s) . The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time, and predecessor as shown in the table. There are 7.5 productive hours available in a day and the manufacturer wishes to produce 400 units. Balance the line by assigning tasks to workstations to fill up as much takt time as possible. Break ties by assigning the longest task first.
 TaskÂ
 TimeÂ
(
s
e
c
)
 PredecessorÂ
 AÂ
45
⋯
 BÂ
50
 AÂ
 CÂ
20
 AÂ
 DÂ
55
 AÂ
 EÂ
15
 DÂ
 FÂ
65
 DÂ
 GÂ
25
 EÂ
 HÂ
35
 B, C, F, GÂ
\begin{array} { | c | c | c | } \hline \text { Task } & \text { Time } ( \mathrm { sec } ) & \text { Predecessor } \\\hline \text { A } & 45 & \cdots \\\hline \text { B } & 50 & \text { A } \\\hline \text { C } & 20 & \text { A } \\\hline \text { D } & 55 & \text { A } \\\hline \text { E } & 15 & \text { D } \\\hline \text { F } & 65 & \text { D } \\\hline \text { G } & 25 & \text { E } \\\hline \text { H } & 35 & \text { B, C, F, G } \\\hline\end{array}
 TaskÂ
 AÂ
 BÂ
 CÂ
 DÂ
 EÂ
 FÂ
 GÂ
 HÂ
​
 TimeÂ
(
sec
)
45
50
20
55
15
65
25
35
​
 PredecessorÂ
⋯
 AÂ
 AÂ
 AÂ
 DÂ
 DÂ
 EÂ
 B, C, F, GÂ
​
​
-Refer to the scenario above. What is the theoretical minimum number of stations that will be used if the line is balanced using the appropriate takt time?
Question 74
Essay
Where should a business consultant position herself on the three axes of contact, customization, and cost.
Question 75
Multiple Choice
Use this scenario for the following question(s) . The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time, and predecessor as shown in the table. There are 7.5 productive hours available in a day and the manufacturer wishes to produce 400 units. Balance the line by assigning tasks to workstations to fill up as much takt time as possible. Break ties by assigning the longest task first.
 TaskÂ
 TimeÂ
(
s
e
c
)
 PredecessorÂ
 AÂ
45
⋯
 BÂ
50
 AÂ
 CÂ
20
 AÂ
 DÂ
55
 AÂ
 EÂ
15
 DÂ
 FÂ
65
 DÂ
 GÂ
25
 EÂ
 HÂ
35
 B, C, F, GÂ
\begin{array} { | c | c | c | } \hline \text { Task } & \text { Time } ( \mathrm { sec } ) & \text { Predecessor } \\\hline \text { A } & 45 & \cdots \\\hline \text { B } & 50 & \text { A } \\\hline \text { C } & 20 & \text { A } \\\hline \text { D } & 55 & \text { A } \\\hline \text { E } & 15 & \text { D } \\\hline \text { F } & 65 & \text { D } \\\hline \text { G } & 25 & \text { E } \\\hline \text { H } & 35 & \text { B, C, F, G } \\\hline\end{array}
 TaskÂ
 AÂ
 BÂ
 CÂ
 DÂ
 EÂ
 FÂ
 GÂ
 HÂ
​
 TimeÂ
(
sec
)
45
50
20
55
15
65
25
35
​
 PredecessorÂ
⋯
 AÂ
 AÂ
 AÂ
 DÂ
 DÂ
 EÂ
 B, C, F, GÂ
​
​
-Refer to the scenario above. How many workstations must be added to increase the output rate to one unit per minute?
Question 76
Multiple Choice
Champion Cooling has just signed a contract to assemble window air conditioners for another company. The list of tasks, including time requirements and immediate predecessors, follows. Each task may not be shortened. Initially, the plan was to make 300 units in an eight hour day but as the summer months approach, Champion Cooling finds themselves far behind in total production. They wish to reconfigure their production line in order to produce maximum output. What should their takt time be?
 TaskÂ
 Time (min) Â
 PredecessorÂ
 Bolt compressor to baseÂ
5
 NoneÂ
 Install coils and linesÂ
6
 Bolt compressor to baseÂ
 Install fan motorÂ
7
 Install coils and linesÂ
 Install switch and thermostatÂ
5
 Install fan motorÂ
 Charge system and testÂ
10
 Install switch and thermostatÂ
 Cosmetic detailingÂ
7
 Charge system and testÂ
\begin{array} { | l | c | c | } \hline \text { Task } & \text { Time (min) } & \text { Predecessor } \\\hline \text { Bolt compressor to base } & 5 & \text { None } \\\hline \text { Install coils and lines } & 6 & \text { Bolt compressor to base } \\\hline \text { Install fan motor } & 7 & \text { Install coils and lines } \\\hline \text { Install switch and thermostat } & 5 & \text { Install fan motor } \\\hline \text { Charge system and test } & 10 & \text { Install switch and thermostat } \\\hline \text { Cosmetic detailing } & 7 & \text { Charge system and test } \\\hline\end{array}
 TaskÂ
 Bolt compressor to baseÂ
 Install coils and linesÂ
 Install fan motorÂ
 Install switch and thermostatÂ
 Charge system and testÂ
 Cosmetic detailingÂ
​
 Time (min) Â
5
6
7
5
10
7
​
 PredecessorÂ
 NoneÂ
 Bolt compressor to baseÂ
 Install coils and linesÂ
 Install fan motorÂ
 Install switch and thermostatÂ
 Charge system and testÂ
​
​
Question 77
Essay
Which poses the greatest underlying managerial challenges - a service that is extremely high on customization, contact, and tangibility or perchance a service that is extremely low on contact, customization and tangibility? Provide an example of a service that fits each space and defend your answer.
Question 78
Essay
Define the terms front room and back room and describe the roles these processes play in service operations. What must operations managers take into consideration when setting up these two processes?