Champion Cooling Has Just Signed a Contract to Assemble Window

Question 76

Multiple Choice

Champion Cooling has just signed a contract to assemble window air conditioners for another company. The list of tasks, including time requirements and immediate predecessors, follows. Each task may not be shortened. Initially, the plan was to make 300 units in an eight hour day but as the summer months approach, Champion Cooling finds themselves far behind in total production. They wish to reconfigure their production line in order to produce maximum output. What should their takt time be?  Task  Time (min)   Predecessor  Bolt compressor to base 5 None  Install coils and lines 6 Bolt compressor to base  Install fan motor 7 Install coils and lines  Install switch and thermostat 5 Install fan motor  Charge system and test 10 Install switch and thermostat  Cosmetic detailing 7 Charge system and test \begin{array} { | l | c | c | } \hline \text { Task } & \text { Time (min) } & \text { Predecessor } \\\hline \text { Bolt compressor to base } & 5 & \text { None } \\\hline \text { Install coils and lines } & 6 & \text { Bolt compressor to base } \\\hline \text { Install fan motor } & 7 & \text { Install coils and lines } \\\hline \text { Install switch and thermostat } & 5 & \text { Install fan motor } \\\hline \text { Charge system and test } & 10 & \text { Install switch and thermostat } \\\hline \text { Cosmetic detailing } & 7 & \text { Charge system and test } \\\hline\end{array}


A) 5
B) 6
C) 7
D) 10

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents