Answer the Following Question(s)using the Information Below

Question 1

Multiple Choice

Answer the following question(s) using the information below.A manufacturing firm is able to produce 1,000 pairs of shoes per hour, at maximum efficiency.There are three eight-hour shifts each day.Due to unavoidable operating interruptions, production averages 800 units per hour.In the month of June the plant actually operated only 25 days due to avoidable shut downs.
-What is the theoretical capacity for the month of April?


A) 600,000 units
B) 720,000 units
C) 744,400 units
D) 576,000 units
E) 480,000 units

Correct Answer:

verifed

Verified