Question 41
Multiple Choice
Which planning technique does not show the relationships among various activities?
Question 42
Essay
Describe the importance of the master plan in systems development.
Question 43
Multiple Choice
Refer to the diagram below,where the numbers next to the arrows refer to the number of days required for completion of the corresponding activity.What is the critical path?
Question 44
Multiple Choice
Suppose an organization is interested in knowing whether the system can be developed and implemented using existing technology.Where should this requirement be considered in a feasibility study?
Question 45
Multiple Choice
Refer to the diagram below,where the numbers next to the arrows refer to the number of days required for completion of the corresponding activity.What is the critical path?
Question 46
Multiple Choice
Suppose an organization is interested in knowing whether it has access to people who can design,implement,and operate the proposed system.Where should this requirement be considered in a feasibility study?
Question 47
Essay
Describe what is a Gantt chart and both of its advantage and disadvantage.
Question 48
Multiple Choice
The most important and frequently re-analyzed part of a feasibility study is the ________ aspect.
Question 49
Multiple Choice
One disadvantage of a Gantt chart is the fact that
Question 50
Multiple Choice
________ requires that all activities and the precedent and subsequent relationships among them be identified.
Question 51
Multiple Choice
A network of arrows and nodes representing project activities that require an expenditure of time and resources and the completion of initiation of activities,respectively,is called
Question 52
Multiple Choice
A feasibility study should first be performed in the ________ stage of the systems development life cycle.
Question 53
Multiple Choice
It is most difficult to quantify ________ when assessing economic feasibility.
Question 54
Multiple Choice
Companies usually accept the project with the ________ when using the payback method to determine a project's economic feasibility.
Question 55
Multiple Choice
________ model is the basic model used to create a framework for an economic feasibility analysis.
Question 56
Multiple Choice
Suppose an organization is interested in knowing whether the system can be developed and implemented in the time allotted.Where should this requirement be considered in a feasibility study?