Services
Discover
Homeschooling
Ask a Question
Log in
Sign up
Filters
Done
Question type:
Essay
Multiple Choice
Short Answer
True False
Matching
Topic
Business
Study Set
Cornerstones of Cost Accounting
Quiz 9: Standard Costing: a Functional-Based Control Approach
Path 4
Access For Free
Share
All types
Filters
Study Flashcards
Practice Exam
Learn
Question 61
Multiple Choice
Gina Production Company uses a standard costing system.The following information pertains to the current year:
Actual factory overhead costs ($ 16,500 is fixed)
$
40
,
125
Actual direct labour costs (11,250 hours)
$
131
,
625
Standard direct labour for 5,500 units:
Standard hours allowed
11,000 hours
Labour rate
$
12.00
\begin{array}{llr} \text {Actual factory overhead costs (\$ 16,500 is fixed) } &\$40,125\\ \text { Actual direct labour costs (11,250 hours) } &\$131,625\\ \text { Standard direct labour for 5,500 units: } &\\ \text {Standard hours allowed } &\text { 11,000 hours} \\ \text {Labour rate } &\$12.00\\\end{array}
Actual factory overhead costs ($ 16,500 is fixed)
Actual direct labour costs (11,250 hours)
Standard direct labour for 5,500 units:
Standard hours allowed
Labour rate
$40
,
125
$131
,
625
11,000 hours
$12.00
The factory overhead rate is based on an activity level of 10,000 units.Standard cost data for 5,000 units is as follows:
Variable factory overhead
$
22
,
500
Fixed factory overhead
13
,
500
‾
Total factory overhead
$
36
,
000
‾
\begin{array}{lr}\text { Variable factory overhead } & \$ 22,500 \\\text { Fixed factory overhead } & \underline{13,500} \\\text { Total factory overhead } & \underline{\$ 36,000} \\\end{array}
Variable factory overhead
Fixed factory overhead
Total factory overhead
$22
,
500
13
,
500
$36
,
000
What is the fixed overhead volume variance for Gina Production Company?
Question 62
Multiple Choice
What is the formula for the fixed overhead spending variance?
Question 63
Multiple Choice
Fixed manufacturing overhead was budgeted at $105,000,and 25,000 direct labour hours were budgeted.If the fixed overhead volume variance was $4,000 unfavourable and the fixed overhead spending variance was $1,500 favourable,what would be the fixed manufacturing overhead applied?
Question 64
Multiple Choice
Fixed manufacturing overhead was budgeted at $200,000,and 25,000 direct labour hours were budgeted.If the fixed overhead volume variance was $8,000 favourable and the fixed overhead spending variance was $6,000 unfavourable,what would be the fixed manufacturing overhead applied?
Question 65
Multiple Choice
Frekko Company collected the following information:
Standard costs per unit:
Variable overhead
4
machine hours @$6 per machine hour
Fixed overhead
4
machine hours
@
$
10
per machine hour
\begin{array}{lr}\text { Standard costs per unit: }\\\text { Variable overhead } & 4 \text { machine hours @\$6 per machine hour } \\\text { Fixed overhead } & 4 \text { machine hours } @ \$ 10 \text { per machine hour }\end{array}
Standard costs per unit:
Variable overhead
Fixed overhead
4
machine hours @$6 per machine hour
4
machine hours
@$10
per machine hour
Actual output
20
,
000
units
Denominator (normal capacity) output
21
,
000
units
Actual machine hours
79
,
000
machine hours
Actual variable overhead cost
$
540
,
000
Actual fixed overhead cost
$
810
,
000
\begin{array}{l}\text { Actual output }&20,000 \text { units } \\\text { Denominator (normal capacity) output } & 21,000 \text { units } \\\text { Actual machine hours } & 79,000 \text { machine hours } \\\text { Actual variable overhead cost } & \$ 540,000 \\\text { Actual fixed overhead cost } & \$ 810,000\end{array}
Actual output
Denominator (normal capacity) output
Actual machine hours
Actual variable overhead cost
Actual fixed overhead cost
20
,
000
units
21
,
000
units
79
,
000
machine hours
$540
,
000
$810
,
000
-Refer to the figure.Using the three variance method,what is the spending variance?
Question 66
Multiple Choice
Frekko Company collected the following information:
Standard costs per unit:
Variable overhead
4
machine hours @$6 per machine hour
Fixed overhead
4
machine hours
@
$
10
per machine hour
\begin{array}{lr}\text { Standard costs per unit: }\\\text { Variable overhead } & 4 \text { machine hours @\$6 per machine hour } \\\text { Fixed overhead } & 4 \text { machine hours } @ \$ 10 \text { per machine hour }\end{array}
Standard costs per unit:
Variable overhead
Fixed overhead
4
machine hours @$6 per machine hour
4
machine hours
@$10
per machine hour
Actual output
20
,
000
units
Denominator (normal capacity) output
21
,
000
units
Actual machine hours
79
,
000
machine hours
Actual variable overhead cost
$
540
,
000
Actual fixed overhead cost
$
810
,
000
\begin{array}{l}\text { Actual output }&20,000 \text { units } \\\text { Denominator (normal capacity) output } & 21,000 \text { units } \\\text { Actual machine hours } & 79,000 \text { machine hours } \\\text { Actual variable overhead cost } & \$ 540,000 \\\text { Actual fixed overhead cost } & \$ 810,000\end{array}
Actual output
Denominator (normal capacity) output
Actual machine hours
Actual variable overhead cost
Actual fixed overhead cost
20
,
000
units
21
,
000
units
79
,
000
machine hours
$540
,
000
$810
,
000
-Refer to the figure.Using the three variance method,what is the budget variance?
Question 67
Multiple Choice
If actual fixed manufacturing overhead was $54,000 and there was a $1,300 unfavourable spending variance and a $1,000 unfavourable volume variance,what would budgeted fixed manufacturing overhead have been?