Solved

Using the Assembly-Line Balancing Procedures for Any Assembly Line Balancing

Question 44

Multiple Choice

Using the assembly-line balancing procedures for any assembly line balancing problem, comparing the theoretical number of work stations (call it X) and the actual number of work stations required using shortest processing time first rule (call it Y) , which of the following is most appropriate?


A) X is always less than Y
B) X is sometimes more than Y
C) X is never less than Y
D) X is sometimes less than Y and sometimes more than Y
E) X is always less than or equal to Y.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents