When balancing an assembly line, which of the following is not a way to reduce the longest task time below the required workstation cycle time?
A) Upgrade the equipment.
B) Assign a roaming helper to support the line.
C) Split the task between two workstations.
D) Speed up the assembly-line transfer mechanism.
E) Use a more skilled worker.
Correct Answer:
Verified
Q48: In the design of retail service layouts,
Q49: This layout groups dissimilar machines to work
Q50: In the design of retail service layouts,
Q51: We would expect to see in a
Q52: Using the assembly-line balancing procedures for any
Q54: The term "servicescape" refers to which of
Q55: (Choose the most appropriate answer from the
Q56: You have just determined the actual number
Q57: Which of the following is not a
Q58: Which of the following basic types of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents