Solved

A Network Has Only One Critical Path and the Slack

Question 69

Short Answer

A network has only one critical path and the slack for noncritical activities is high.This network would appear to have a _______ level of sensitivity.

Correct Answer:

verifed

Verified

low
Explanation: Network sensitivity is ...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents