An activity cannot begin until ALL preceding connected activities have been completed.
Correct Answer:
Verified
Q10: In developing a project network, neither looping
Q11: It is possible for a project network
Q12: Experience suggests that when there are multiple
Q13: The critical path is the shortest path
Q14: The WBS identifies dependencies, the sequencing of
Q16: When completing a forward pass, you carry
Q17: It is acceptable for arrows to cross
Q18: If the project has a duration of
Q19: Using free slack does not delay any
Q20: The forward pass through a project network