All of the following are benefits of scheduling resources before project implementation EXCEPT
A) It allows time for considering reasonable options if resource constraints do exist.
B) The project completion date can be established.
C) Work packages can be time-phased.
D) It allows managers to share resources with other project managers if it is requested without negatively impacting their project.
E) It ensures low network sensitivity.
Correct Answer:
Verified
Q27: When looking at the critical path for
Q28: A project budget report is showing our
Q30: These are all guidelines a project manager
Q31: In a resource-constrained project the second priority
Q33: When deciding which staff to team-up to
Q34: Tony has realized that two activities in
Q35: Having one person responsible for performing several
Q37: This is used to compare the cost
Q44: Why is it necessary to have a
Q52: Which of the following is NOT one
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents