Which of the following is not true about network diagrams?
A) Activities can be shown on the arrow
B) Activities can be shown on the nodes
C) An activity can have more than one predecessors
D) Movement from one activity to another can go forward or backward
E) Starting activities have no predecessors
Correct Answer:
Verified
Q24: Additional resources can rarely be used to
Q25: Which of the following statements accurately describes
Q26: A contingency plan should be developed for
Q27: In a PERT analysis,the "most likely time"
Q28: Which is true about the critical path?
A)It
Q30: A project risk assessment plan involves developing
Q31: Clear and measurable goals help projects to
Q32: The only significant risk involved in project
Q33: Being an expert in information integration,project scope,time
Q34: Activities with zero slack are critical activities.
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents