In a PERT analysis,the "most likely time" is the minimum possible time required to complete an activity.
Correct Answer:
Verified
Q22: Projects generally have all the following characteristics
Q23: Which of the following is not a
Q24: Additional resources can rarely be used to
Q25: Which of the following statements accurately describes
Q26: A contingency plan should be developed for
Q28: Which is true about the critical path?
A)It
Q29: Which of the following is not true
Q30: A project risk assessment plan involves developing
Q31: Clear and measurable goals help projects to
Q32: The only significant risk involved in project