Question 81

Multiple Choice

What is the correct sequence of the purchase-to-pay process?


A) purchase order processing; goods receipt; invoice verification; payment processing; requirements determination
B) requirements determination; purchase order processing; goods receipt; invoice verification; payment processing
C) purchase order processing; requirements determination; goods receipt; invoice verification; payment processing
D) requirements determination; purchase order processing; invoice verification; goods receipt; payment processing

Correct Answer: