A project consists of nine major activities,as shown.There are three separate paths in the network:
a-c-f,b-d-g,and e-h-i.
(i)What is expected project duration time?
(ii)Determine the probability that the project will take more than 35 weeks to complete.(All durations are in weeks.)
Correct Answer:
Verified
(ii)P(Pro...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q103: Activity E has an optimistic duration of
Q104: What is the probability that the critical
Q112: Q112: Activity D has an optimistic duration of Q113: Given the network diagram above,determine each of Q114: What is the estimated expected (mean)duration for Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents