Given the network diagram,determine the probability that the project will finish within 19 weeks of its start.Durations on the diagram are in weeks.
Correct Answer:
Verified
Related Questions
Q103: Activity E has an optimistic duration of
Q107: What is the probability that this project
Q108: What is the estimated standard deviation of
Q109: Determine the amount of slack in each
Q113: Given the network diagram above,determine each of
Q114: What is the estimated expected (mean)duration for