Solved

Use the Information in the Table and Assume That a Worker

Question 42

Multiple Choice

Use the information in the table and assume that a worker is expected to devote half-time (four hours per day) to this project with work taking place on a 5-day-per-week basis.Which week has the lowest resource usage?  Activity  Duration  Predecessor  A 5 days B4 days  A C5 days  A D6 days BE6 days C,DF6 days E\begin{array} { | l | l | l |} \hline \text { Activity } & \text { Duration } & \text { Predecessor } \\\hline \text { A } & 5 \text { days } & - \\\hline B & 4 \text { days } & \text { A } \\\hline C& 5 \text { days } & \text { A } \\\hline \mathrm { D } & 6 \text { days } & B \\\hline E & 6 \text { days } & C ,D \\\hline F & 6 \text { days } & E \\\hline\end{array}


A) Week 6
B) Week 2
C) Week 4
D) Week 3

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents