Multiple Choice
-The project represented by this resource load chart has a maximum limit of 6 units of resource activity in any day.Which activity could be split to help the project team finish on time and meet the resource cap?
A) Activity A
B) Activities B and C
C) Activities D and E
D) Activity E and F
Correct Answer: