A project is represented by the activity durations (in days,estimated at 90% likelihood of completion) and precedence requirements shown in the table.How many project buffers are needed if this project is managed using critical chain methodology?
A) 0
B) 1
C) 2
D) 3
Correct Answer:
Verified
Q73: A project is represented by the
Q74: A project is represented by the
Q75: A project consists of six consecutive
Q76: A project is represented by the
Q77: The buffers supplied to non-critical paths in
Q79: A project is represented by the
Q80: Subcontractor deliveries are difficult to schedule with
Q81: A resource constraint can be exploited using
Q82: A project that consists of six
Q83: An important element in critical chain scheduling