A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the length of the project buffer if this project is managed using critical chain methodology?
A) 13.5
B) 22.5
C) 11.25
D) 9.0
Correct Answer:
Verified
Q74: A project is represented by the
Q75: A project consists of six consecutive
Q76: A project is represented by the
Q77: The buffers supplied to non-critical paths in
Q78: A project is represented by the
Q80: Subcontractor deliveries are difficult to schedule with
Q81: A resource constraint can be exploited using
Q82: A project that consists of six
Q83: An important element in critical chain scheduling
Q84: Drum buffers are:
A)A safety margin separating different
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents