Successful implementation of CCPM depends on first:
A) Identifying the critical chain that meanders through the project organization's portfolio of projects.
B) Identifying the constraint that holds hostage the project organization's other resources.
C) Examining and changing the culture of the project organization.
D) Exploiting the drum by using it to subordinate the existing PERT network.
Correct Answer:
Verified
Q46: Alexander Demetrius Dickson,ADD to his friends,has three
Q47: Your next project consists of 10 consecutive
Q48: List any three criticisms of critical chain
Q49: An important departure from traditional project management
Q50: The Central Limit Theorem states that if
Q52: A project consists of four activities
Q53: A project consists of four activities
Q54: What is aggregated buffer and how can
Q55: Which statement about critical chain methodology is
Q56: Once the organization elevates its constraint,its system
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents