A project consists of four activities with information as shown in the table.What is the overall variance of the project's duration?
A) 13
B) 17
C) 26
D) 35
Correct Answer:
Verified
Q48: List any three criticisms of critical chain
Q49: An important departure from traditional project management
Q50: The Central Limit Theorem states that if
Q51: Successful implementation of CCPM depends on first:
A)Identifying
Q52: A project consists of four activities
Q54: What is aggregated buffer and how can
Q55: Which statement about critical chain methodology is
Q56: Once the organization elevates its constraint,its system
Q57: Your next project consists of 8 consecutive
Q58: The critical chain is usually the same