A project manager is estimating costs on her video game development project.She utilizes total costs from a similar project that was completed last year to estimate the costs on her current project.This is an example of:
A) Bottom-up estimation
B) Rough order magnitude estimation
C) Analogous estimation
D) Parametric estimation
Correct Answer:
Verified
Q22: The order of magnitude cost estimate is
Q23: When asked to provide an estimate of
Q24: What learning rate is being demonstrated if
Q25: It took 44 hours of analysis to
Q26: Explain the difference between normal and expedited
Q28: Rank the four different types of cost
Q29: Effective comparative estimates rely most heavily on:
A)An
Q30: An order of magnitude estimate is usually
Q31: Which of these estimates should be the
Q32: If a project manager is using a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents