company must perform a maintenance project consisting of seven activities.The activities,their predecessors,and their respective time estimates are presented below:
Using CPM,what is the Latest Finish Time for the last activity in this project (i.e. ,the total time to complete the project)
A) 9 days
B) 10 days
C) 11 days
D) 12 days
E) 13 days
Correct Answer:
Verified
Q22: When reducing the planned duration of a
Q32: Project management software available today combines CPM
Q40: project milestone is a specific event to
Q41: company must perform a maintenance project consisting
Q42: listing of immediate predecessor activities is important
Q47: series of projects that are organized in
Q50: What is a work breakdown structure?
A)A list
Q51: You have been placed in charge of
Q56: PERT is an abbreviation for which of
Q58: You are looking at a chart that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents