Time variance is calculated by subtracting actual time used for work performed from scheduled time for work performed.
Correct Answer:
Verified
Q12: A major assumption in project network analysis
Q13: Schedule variance is the difference between budgeted
Q14: Merge node bias occurs where the project
Q15: When delays occur owing to technical difficulties,
Q16: Gantt charts fail to indicate the interdependence
Q18: The term 'late finish' refers to the
Q19: Before calculating a late start time for
Q20: The critical path refers to the sequence
Q21: For a project with uncertain activity times,
Q22: Projects are terminated for all of the