Multiple Choice
Figure 8-4 Project Crashing Information
-Consider the project crashing information presented in Figure 8-4.What is the total cost to complete this project in 7 days if crashed in the most cost efficient manner?
A) $ 180
B) $ 220
C) $ 240
D) $ 270
Correct Answer:
Verified