If the project manager changes an activity on the critical path to start at a later date,then the whole project will end at a later date.
Correct Answer:
Verified
Q5: The length of time to perform an
Q6: The "start-to-start" logical relationship used in activity
Q7: A mandatory dependency is a logical relationship
Q8: There is often terrific pressure to complete
Q9: In the enumeration method the project schedule
Q11: While the lowest level of decomposition in
Q12: A Gantt chart is a horizontal bar
Q13: In order for activities to be useful
Q14: PERT refers to Program Evaluation and Review
Q15: GANTT refers to the Generalized Activity Network
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents