While the lowest level of decomposition in a WBS is the work package,work packages can still be decomposed further into work activities.
Correct Answer:
Verified
Q6: The "start-to-start" logical relationship used in activity
Q7: A mandatory dependency is a logical relationship
Q8: There is often terrific pressure to complete
Q9: In the enumeration method the project schedule
Q10: If the project manager changes an activity
Q12: A Gantt chart is a horizontal bar
Q13: In order for activities to be useful
Q14: PERT refers to Program Evaluation and Review
Q15: GANTT refers to the Generalized Activity Network
Q16: The primary advantage of PERT is that