The overall project is considered to be the first level of the WBS.All of the following methods can be used to organize the second level of the WBS EXCEPT:
A) Organized by project phase.
B) Organized by design components / deliverables.
C) Organized by work function./ subproject
D) Organized by activities and tasks
Correct Answer:
Verified
Q21: All of the following statements correctly describe
Q22: Which of the following is NOT a
Q23: The method of dividing the project scope
Q24: The Work Breakdown Structure (WBS)is a framework
Q25: The project scope planning processes include all
Q27: The work component at the lowest level of
Q28: Once the plan baseline has been approved
Q29: On agile projects,the scope definition begins with
Q30: Work Breakdown Structures typically include one or
Q31: This technique is an iterative process that identifies
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents