Solved

Work Breakdown Structures Typically Include One or More Intermediate Levels

Question 30

Multiple Choice

Work Breakdown Structures typically include one or more intermediate levels.Which of the following statements correctly describe the nature of these intermediate levels?​ 


A)  They generally represent items that need to be created in order to produce the final deliverables. 
B)  They generally represent the raw materials required to create the final deliverables. 
C)  They generally represent the resource assignments to create the final deliverables. 
D)  They generally represent the sequence and timing of work packages

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents