Which of the following is NOT one of the steps that managers take to mitigate scheduling problems?
A) Lot splitting can be used for large orders when there are significant differences in job processing times.
B) Scheduling should be based on the capacity of the operations that are bottlenecks if there are capacity constraints in the facility.
C) The due dates set for order delivery should be realistic and should take existing loads on work centers and available capacities into account.
D) Scheduling should be focused on customer orders and delivery by due dates.
Correct Answer:
Verified
Q74: In DBR (drum-buffer-rope),which of the following is
Q75: _ is a planning and scheduling method
Q76: The two different ways of assessing batch
Q77: From a sustainability perspective,one of the key
Q78: Resource use in a manufacturing process is
Q80: Which of the following is NOT an
Q81: The average tardiness for jobs listed
Q82: The average number of jobs in
Q83: The average flow time for jobs
Q84: The average number of jobs in
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents