In DBR (drum-buffer-rope) ,which of the following is the mechanism that synchronizes or subordinates all other resources and decisions to the activities of the drum in order to maximize its effectiveness?
A) drum
B) buffer
C) rope
D) schedule
Correct Answer:
Verified