Which type of estimate should be used if the cost estimate for a project is used a basis for contract awards and performance reporting?
A) budgetary
B) definitive
C) rough order of magnitude
D) analogous
Correct Answer:
Verified
Q41: Which costs are difficult to measure in
Q42: Which type of estimate uses the actual
Q43: Which statement is true of contingency reserves?
A)
Q44: Which statement is true of a order
Q45: Which reserves allow for future situations that
Q47: What is the first step in project
Q48: What type of estimate is used for
Q49: Newtech Inc. hires John for the position
Q50: Which statement is true of bottom-up estimates?
A)
Q51: What type of estimate is a cost