Which statement is true of bottom-up estimates?
A) They are based on the actual cost of a previous, similar project.
B) They are also known as parametric estimating.
C) They are most accurate when they involve large, extensive work items.
D) They are time-intensive and expensive to develop.
Correct Answer:
Verified