The critical path is the _____ path through a network diagram, and it represents the _____ amount of slack or float.
A) longest; longest
B) longest; shortest
C) shortest; longest
D) shortest; shortest
Correct Answer:
Verified
Q47: Which technique involves network diagramming and is used primarily
Q48: Which type of dependencies are inherent in
Q49: Which is true of a finish-to-finish dependency?
A)
Q50: Which network diagramming technique uses boxes to
Q51: What is the latest possible time an
Q53: Which dependencies involve relationships between project and
Q54: What term is used for the amount
Q55: Which provide a standard format for displaying
Q56: Which is true of dummy activities?
A) They
Q57: In project schedule management, the ultimate goal